CONSTRUCTION WORKS STATUS FOR PARCULUI20, JULY 2020

Work status: the works on Parcului20`s construction site continued, according to the schedule, throughout this period, in full compliance with the measures imposed by the authorities to prevent the spread of COVID-19, along with our own health and safety measures that Cordia implements in all its construction sites.

 

Thus, by mid-July 2020, the following works have been completed:

  • Partitions throughout the building
  • Mechanized pouring of screed throughout the building
  • Applying plaster throughout the building
  • Installation of joinery, including glass, throughout the building
  • Installation of waterproofing on non-circulating terraces
  • Installation of the basalt wool thermal system on all facades, currently decorative paint is being applied

 

The following works are currently underway:

  • Waterproofing and ceramic tiles installation on circulating terraces and balconies;
  • Marble tiles installation on common spaces up to the 7th floor;
  • Parquet installation up to the 5th floor;
  • Application of primer for walls and ceiling ground floor up to the 9th floor;
  • Installation of ceramic tiles up to the 10th floor;
  • Waterproofing on non-circulating terrace over the 11D floor;
  • Installation of apartments` entrance doors up to the 11th floor;
  • Installation of ribbon and bond structure on all facades;
  • Installation of architectural balconies structure;
  • Sanitary, electrical and thermal installations up to the 11D floor in apartments and common areas, including technical spaces;
  • External networks

 

For more information on the work status of the project, please call 075 777 55 11, e-mail us at [email protected] or visit us at the sales office in 2 Expoziției Blvd.