The first month of summer brings us closer to the delivery of the first apartments in the second phase of PARCULUI20, in which 80% of the units have already found an owner. All apartments are efficiently designed (partitioned), with generous terraces and balconies, ample storage space and work-from-home areas.
You can visit the first apartment building in which the residents have lived for more than a year, the three-room and duplex showroom apartments, the common spaces, and the ones dedicated to relaxation and leisure. Come to our sales office to discuss what smart and energy efficient apartments mean and to visit the second phase and the showroom apartment arranged at the ground floor.
We are closely following the progress of the site to keep you up to date with the evolution of the construction works.
We completed:
- wall and ceiling finishing plaster on ground floor up to 11th duplex floor, we have checked flatness, angularity of the walls and support for washable paint
- 1st and 2nd layer of washable paint on the 1st floor, 2nd floor, 3rd floor, 4th floor, 5th floor, 6th floor, 7th floor, 8th floor, 9th floor and 10th floor
- electrical appliances socket installation on 1st floor, 2nd floor, 3rd floor, 4th floor, 5th floor, 6th floor, 7th floor, 8th floor, 9th floor and 10th floor
- Rockwool installation on all the facades – to date 100% of façade was checked considering Rockwool works, flatness check, support preparation for the decorative paint primer (except the ground floor area)
- Decorative paint on south-vest façade (except the ground floor area)
- Decorative paint on north-vest façade (except the ground floor area and on the exterior elevators)
- Decorative paint on north-east façade (except de ground floor area)
- Bond works, vertical elements
- Horizontal elements
- Interior doors installation on ground floor up to 8th floor
- Entrance doors installation on ground floor up to 11th duplex floor
- Parquet installation on the 1st floor up to 8th floor
- Stone works on hallways on 1st floor up to 8th floor
- Ceramic tiles installation on the ground floor up to 6th floor
- Elevators’ installation
- Works on showroom apartment
In progress:
- 1st layer of washable paint on the 11th and 11th duplex floor
- MEP works in the basement up to 11th duplex floor
- electrical appliances socket installation on 11th floor and 11th duplex floor
- Decorative paint on south-east façade
- Bond steel structure and sub-structure works
- Exterior landscaping works
- Staircase balustrade installation
- Stone works on hallways on ground floor and 9th floor and on the staircases
- Ceramic tiles installation on the 7th up to 11th duplex floor
- Special works, aluminum balcony elements
The second phase will be delivered this year, together with the final arrangement of the interior garden of over 3,000 sqm. Come and visit us at the sales office in Bulevardul Expoziției Nr.2, Sector 1, Bucharest. You can find us there from Monday to Friday from 10:00 to 18:00 and on Saturday from 10:00 to 14:00. You can set up an appointment by calling us: 0759 890 890/ 031 069 9740.